We have been introducing our modular cleanroom with fast installation as the main advantage. But how quickly can an Airkey FastIns Modular Cleanroom be constructed? Let the facts speak for themselves.
This modular cleanroom is 198.3 m² with an internal height of 3 meters, under ISO 7 cleanroom classification. It features a large span, yet is designed as a free-standing structure.
In September, our customer in Zebrak, Czech Republic, received the cleanroom shipment on the 6th. After site preparation, construction began on September 7th.
A total of 5 workers participated in the installation, none of whom had prior experience building cleanrooms. Following the provided installation instructions, they assembled the structure step by step: base frames, wall frames, walls and windows, ceiling grids, and FFUs (Fan Filter Units). With the help of installation labels, the entire construction was completed in just 7 days.
Once construction was finished, immediate testing was conducted, including illuminance and particle count tests in the as-built state. This ensured that the modular cleanroom was completed quickly without compromising on quality.
So, how fast can an Airkey FastIns Modular Cleanroom be assembled? In this case, it took just 7 days to construct a 200 m² cleanroom with 5 people. How many days will it take for yours? Try and find out!
Project Specifications:
- Project: E-cigarette manufacturing cleanroom
- Area: 198.3 m²
- Internal height: 3m
- Class: ISO 7 (Class 10000)
- Design temperature/RH: 18-25°C / 50±10%
- Industry: E-cigarette liquid
- Location: Prague, Czech Republic